4 Lift Shaft Refurbishments

CBES has recently completed a £350k refurbishment program for NB Real Estate at the Crescent Centre, Bristol. This was a difficult project as some of the existing lifts had to be kept operational while new lifts were fitted. There were also noise constraints which meant that work had to be undertaken out of hours. The Project was completed under budget and 4 weeks a head of schedule.