Lift refurbishment
Budget: £50,000
Duration: 12 Weeks
Replacement of existing lift and fast track refurbishment of the lift shaft to enable the installation of OTIS generation 2 lift. Speed was esential as the care home was occupied.
Budget: £50,000
Duration: 12 Weeks
Replacement of existing lift and fast track refurbishment of the lift shaft to enable the installation of OTIS generation 2 lift. Speed was esential as the care home was occupied.
Budget: £250,000
Working with Triangle Lifts, we constructed 6 lift shafts in the cheltenham area. The construction and extension of the existing staircase and lobby to enable a landing area.
This was a listed building, and our task was modernise an existing lift shaft. The dificulty with this was that the building was a listed building. This meant that the lift had to be athetically in keeping with the character of the building. Also we had to re route the drains and divert them outside, whilst ensuring that the drainage was aesthetically in character with the listed building.
For the various care homes under OTIS, we completed a number of tasks. We removed the existing hydraulic lifts, and completed building works to comply with British standards for care homes. Due care and consideration was taken when erecting the hoardings. Some of the recent care homes that we have completed work for are: The Paddock in Muswell Hill London, Epworth Court in Swindon, Moreton Care Home in Exmouth, Walcot Care Home in Bath.