Diechmann Shoes, Cardiff

}?>

Scenic Lift installation

Project budget: £70,000

Duration: 14 weeks

At their new store in the St Davids Shopping Mall Cardiff our specialist team were contracted to design and form a steel frame and glass scenic lift into an existing shop unit. The project was a great visual success despite a tight schedule and a complex glass installation process.

 

 

Crescent Centre, Bristol

}?>

Crescent Centre, Bristol

4 Lift Shaft Refurbishments

CBES has recently completed a £350k refurbishment program for NB Real Estate at the Crescent Centre, Bristol. This was a difficult project as some of the existing lifts had to be kept operational while new lifts were fitted. There were also noise constraints which meant that work had to be undertaken out of hours. The Project was completed under budget and 4 weeks a head of schedule.